Crewe Green Roundabout – What’s Happening?

The main construction works for the scheme will begin in late January 2018, with the new roundabout fully opened to traffic in October 2018. Landscaping of the site will take place during November 2018.

The construction work will take place in 3 phases:

  • Phase 1: end of January to April 2018 (12 weeks)
  • Phase 2: April/May to July 2018 (12 weeks)
  • Phase 3: July/August to November 2018 (16 weeks)

Meet the Contractor event

Cheshire East will be holding a ‘Meet the Contractor’ event on:

Thursday 18 January 2pm to 8pm at The Hunters Lodge, Sydney Road, Crewe, CW1 5LU